By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
A public log of 7 European data center land and site transactions with their published terms: 3 completed, the rest agreed or non-binding. Each row separates grid MW from IT MW and completed prices from offers, because the two are often mixed up. Prices range from €11 million for a 25 MW powered plot near Madrid to €225 million for a permitted former power-plant site in the UK. ActivumSG
Download this dataset: JSON · CSV · Markdown — CC BY 4.0, attribution to Ampervia
Findings
One non-binding offer pays €1m per MW of RTB IT capacity; another pays €1.5m per site upfront and €1.5m more at RTB.
4 of 7 rows have no disclosed price; the stage and capacity basis are still informative.
A grid power agreement includes cooling and losses; RTB offers are often quoted per IT MW. The table never divides one by the other.
Non-binding offers can change after due diligence; they are labelled as such.
The deals
| Date | Location | Land | Capacity | Capacity basis | Price | Price per MW | Stage | Status | Buyer ← seller | Sources |
|---|---|---|---|---|---|---|---|---|---|---|
| 2024-07 | Meco, Madrid, Spain | 17,650 m² | 25 MW | grid power agreement | €11m | ≈€440k per grid MW | Powered land (power agreement + dual feed) | Completed | Pure DC ← ActivumSG | [1] [2] |
| 2024-10 | Vicálvaro, Madrid, Spain | 22,000 m² | 40 MW | grid supply agreement | Not disclosed | — | Powered land (secured power rights) | Completed (price not disclosed) | Edgnex (DAMAC) ← ActivumSG | [1] [2] |
| 2026-05 | Didcot A, Oxfordshire, UK | — | — | not disclosed | €225m | — | Planned campus with planning permission (granted July 2025) | Completed | Undisclosed hyperscaler ← RWE | [1] [2] |
| 2026-06 | Mora, Toledo, Spain (Malpica project) | — | 300 MW | IT capacity certified ready-to-build | €300m | — | Pre-RTB; price payable per RTB MW at closing | Non-binding offer (24 June 2026) | Spark AI Foundry Holdings ← EdgeMode | [1] [2] |
| 2026 | Córdoba, Palma del Río, Vianos, Cáceres, Spain | — | — | per leased IT MW | Not disclosed | — | Land interests; staged to RTB and leasing | Non-binding term sheet | Pure DC ← EdgeMode | [1] [2] |
| 2026-06 | Pori, Finland | 260,000 m² | — | secured grid capacity (MW not disclosed) | Not disclosed | — | Zoning, building permits and secured grid capacity | Agreed sale (price not disclosed) | Undisclosed European operator ← Polarnode | [1] |
| 2026-08 | Milan area, Italy | 23,000 m² | 30 MW | potential capacity (grid application submitted) | Not disclosed | — | Land secured; grid application filed | Acquired by developer (price not disclosed) | Magnora ← Not disclosed | [1] |
Method and inclusion rules
- Only transactions with a public source; each row links them.
- Capacity is recorded with its basis (grid, IT, potential); price per MW is computed only for grid-basis rows with both figures.
- Status distinguishes completed sales from agreed, non-binding or undisclosed deals.
- Ampervia’s own candidate sites are never listed here.
Corrections and revisions
Spotted an error or a missing public deal? Write to team@ampervia.com. Revision log: 2026-10-12 — first edition, 7 rows.
Questions
Why include deals without a price?
Is this all European deals?
Sources
- ActivumSG — €11m powered land sale to Pure DC
- BSIC — The connection premium: pricing Europe’s powered land
- BeBeez — EdgeMode looks to sell data center development sites in Spain
- DCD — Edgnex to develop 40 MW data center in Madrid
- DCD — Magnora acquires land outside Milan
- DCD — Pure DC acquires land in Madrid
- DCD — RWE completes sale of planned Didcot data campus
- Data Central — Pori turns powered land into a sale
- Data Central — Spanish data centre land starts trading like power
- DataTech — EdgeMode agrees €300m non-binding sale of Spain project
- Expansión — Edgemode, Mora (Toledo) pre-agreement (30 Jun 2026)
- Iberian Property — DAMAC buys land in Madrid for €400m data centre
Ampervia Capital