By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
A public log of 11 European data center land and site transactions with their published terms: 7 completed, the rest agreed or non-binding. Each row separates grid MW from IT MW and completed prices from offers, because the two are often mixed up. Prices range from €11 million for a 25 MW powered plot near Madrid to £203 million for a restored former power-station site with a 300 MW grid connection in the UK. AVENTOS press release
Download this dataset: JSON · CSV · Markdown — CC BY 4.0, attribution to Ampervia
Findings
One non-binding offer pays €1m per MW of RTB IT capacity; another pays €1.5m per site upfront and €1.5m more at RTB.
6 of 11 rows have no disclosed price; the stage and capacity basis are still informative.
A grid power agreement includes cooling and losses; RTB offers are often quoted per IT MW. The table never divides one by the other.
Non-binding offers can change after due diligence; they are labelled as such.
The deals
| Date | Location | Land | Capacity | Capacity basis | Price | Price per MW | Stage | Status | Buyer ← seller | Sources | Case |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 2023-11 | Maintal (Frankfurt–Hanau), Germany | 37,830 m² | — | not disclosed | €40m | — | Business park after change of use | Completed | Data center developer (local press: EdgeConneX) ← Sirius Real Estate | Sources (3)Europe Real EstateEurope Real Estate — Sirius sells Maintal industrial park for €40.1m (Nov 2023)↗UKREiiFUKREiiF — Sirius disposes of Maintal industrial park at premium to book value (7 Nov 2023)↗Hanauer AnzeigerHanauer Anzeiger — Maintal councillors debate data centers (EdgeConneX at the former Sirius Business Park)↗ | Case study |
| 2024-07 | Meco, Madrid, Spain | 17,650 m² | 25 MW | grid power agreement | €11m | ≈€440k per grid MW | Powered land (power agreement + dual feed) | Completed | Pure DC ← ActivumSG | Sources (2) | Case study |
| 2024-10 | Vicálvaro, Madrid, Spain | 22,000 m² | 40 MW | grid supply agreement | Not disclosed | — | Powered land (secured power rights) | Completed (price not disclosed) | Edgnex (DAMAC) ← ActivumSG | Sources (2) | Case study |
| 2025 | Kelsterbach (Frankfurt), Germany | 50,250 m² | — | not disclosed | €50m | — | Operating shell-and-core data center (built 1989) | Completed | Undisclosed ← Keppel DC REIT | Case study | |
| 2025-09 | Corsico (Milan), Italy | — | 13.6 MW | planned data center capacity | Not disclosed | — | Brownfield with existing high-capacity connections | Completed (price not disclosed) | Retelit ← Marcegaglia | Sources (2)Pambianco Real EstatePambianco Real Estate — Marcegaglia sells Corsico industrial site to Retelit (Sep 2025)↗RetelitRetelit — groundbreaking of the Milan Corsico data centre (2026)↗ | Case study |
| 2025-11 | Didcot A, Oxfordshire, UK | 230,000 m² | 300 MW | grid connection | £203m | ≈£677k per grid MW | Planned campus with hybrid planning permission (July 2025) | Completed | Hyperscaler (analysts: Amazon) ← RWE | Sources (2) | Case study |
| 2025-12 | Siemensstadt, Berlin, Germany | 28,400 m² | — | 63 MVA grid connection contract | Not disclosed | — | Plot with signed grid connection contract | Completed (price confidential) | Tristan Capital Partners (EPISO 6) ← Aventos | AVENTOS press release | Case study |
| 2026 | Córdoba, Palma del Río, Vianos, Cáceres, Spain | — | — | per leased IT MW | Not disclosed | — | Land interests; staged to RTB and leasing | Non-binding term sheet | Pure DC ← EdgeMode | Sources (2) | — |
| 2026-06 | Mora, Toledo, Spain (Malpica project) | — | 300 MW | Proposed IT capacity; price payable per MW only once certified ready-to-build | €300m | — | Pre-RTB; price payable per RTB MW at closing | Non-binding offer (24 June 2026) | Spark AI Foundry Holdings ← EdgeMode | Sources (2)DataTechDataTech — EdgeMode agrees €300m non-binding sale of Spain project↗ExpansiónExpansión — Edgemode, Mora (Toledo) pre-agreement (30 Jun 2026)↗ | Case study |
| 2026-06 | Pori, Finland | 260,000 m² | — | secured grid capacity (MW not disclosed) | Not disclosed | — | Zoning, building permits and secured grid capacity | Agreed sale (price not disclosed) | Undisclosed European operator ← Polarnode | Data Central | — |
| 2026-08 | Milan area, Italy | 23,000 m² | 30 MW | potential capacity (grid application submitted) | Not disclosed | — | Land secured; grid application filed | Acquired by developer (price not disclosed) | Magnora ← Not disclosed | — |
Method and inclusion rules
- Only transactions with a public source; each row links them.
- Capacity is recorded with its basis (grid, IT, potential); price per MW is computed only for grid-basis rows with both figures.
- Status distinguishes completed sales from agreed, non-binding or undisclosed deals.
- Ampervia’s own candidate sites are never listed here.
Field dictionary
| Field | Meaning |
|---|---|
| date | Month the sale completed or the offer was announced (YYYY-MM) |
| place | Town or district, region and country |
| land_m2 | Site area in square metres, where published |
| mw | Capacity figure published with the deal |
| mw_basis | What that capacity is: grid power agreement or connection, IT load, planned capacity, or not disclosed |
| price_eur | Price in euros, where the source gives one |
| price_text | Price in the source’s own currency when it is not in euros (for example £203m) |
| stage | What was sold: powered land, permitted site, brownfield with connections, ready-to-build project |
| status | Completed, agreed, non-binding, or price not disclosed |
| buyer / seller | As named in the sources; analyst attributions are marked |
| note | Caveats, including where reports conflict |
| sources | URLs of the documents each row is taken from |
Limitations
- Not a complete record of European deals: only transactions with a public source that Ampervia has checked.
- Grid MW and IT MW are different measures. Price per MW is computed only where both the price and a grid capacity are published, and never across the two bases.
- Prices in pounds are not converted to euros; the price_text field keeps the source currency.
- Non-binding offers can change or lapse after due diligence.
- Sale prices are not seller profit: entry prices and costs are usually undisclosed.
Version history and corrections
- 2026-10-13: Didcot corrected to £203 million paid, from RWE’s Annual Report 2025 (earlier press reports, and this dataset, had shown RWE’s €225 million book gain as the price); 300 MW grid connection and 23 ha added. Rows linked to case studies. 11 rows.
- 2026-10-12: first edition.
Spotted an error or a missing public deal? Write to team@ampervia.com.
Questions
Why include deals without a price?
Is this all European deals?
Sources
AVENTOS press releaseActivumSG
BeBeezSources (5)
DCDDCD — Edgnex to develop 40 MW data center in Madrid↗
DCDDCD — Keppel sells Frankfurt data center for €50m (Feb 2025)↗
DCDDCD — Magnora acquires land outside Milan↗
DCDDCD — Pure DC acquires land in Madrid↗
DCDDCD — RWE completes sale of planned Didcot data campus (Nov 2025)↗Sources (2)Data CentralData Central — Pori turns powered land into a sale↗Data CentralData Central — Spanish data centre land starts trading like power↗DataTechEurope Real EstateExpansiónHanauer AnzeigerIberian PropertyPambianco Real Estate
RWERetelitUKREiiF