 "updated": "2026-10-12",
 "license": "CC BY 4.0",
 "deals": [
  {
   "date": "2024-07",
   "place": "Meco, Madrid, Spain",
   "land_m2": 17650,
   "mw": 25,
   "mw_basis": "grid power agreement",
   "price_eur": 11000000,
   "stage": "Powered land (power agreement + dual feed)",
   "status": "Completed",
   "buyer": "Pure DC",
   "seller": "ActivumSG",
   "note": "",
   "sources": [
    "https://www.activumsg.com/activumsg-completes-11m-powered-land-sale-pure-dc/",
    "https://www.datacenterdynamics.com/en/news/pure-dc-acquires-land-in-madrid-spain-for-data-center-development/"
   ]
  },
  {
   "date": "2024-10",
   "place": "Vicálvaro, Madrid, Spain",
   "land_m2": 22000,
   "mw": 40,
   "mw_basis": "grid supply agreement",
   "price_eur": null,
   "stage": "Powered land (secured power rights)",
   "status": "Completed (price not disclosed)",
   "buyer": "Edgnex (DAMAC)",
   "seller": "ActivumSG",
   "note": "Planned €400m data center; ~22,000–23,000 m² reported.",
   "sources": [
    "https://www.datacenterdynamics.com/en/news/damacs-edgnex-to-develop-40mw-data-center-in-madrid-spain/",
    "https://www.iberian.property/news/logistics/damac-group-buys-land-in-madrid-to-build-a-eur400m-data-centre/"
   ]
  },
  {
   "date": "2026-05",
   "place": "Didcot A, Oxfordshire, UK",
   "land_m2": null,
   "mw": null,
   "mw_basis": "not disclosed",
   "price_eur": 225000000,
   "stage": "Planned campus with planning permission (granted July 2025)",
   "status": "Completed",
   "buyer": "Undisclosed hyperscaler",
   "seller": "RWE",
   "note": "Former coal/oil power plant site.",
   "sources": [
    "https://www.datacenterdynamics.com/en/news/rwe-completes-sale-of-planned-didcot-data-campus-in-oxfordshire-uk/",
    "https://bsic.it/the-connection-premium-pricing-europes-powered-land/"
   ]
  },
  {
   "date": "2026-06",
   "place": "Mora, Toledo, Spain (Malpica project)",
   "land_m2": null,
   "mw": 300,
   "mw_basis": "IT capacity certified ready-to-build",
   "price_eur": 300000000,
   "stage": "Pre-RTB; price payable per RTB MW at closing",
   "status": "Non-binding offer (24 June 2026)",
   "buyer": "Spark AI Foundry Holdings",
   "seller": "EdgeMode",
   "note": "€1 million per MW of RTB IT capacity; headline up to €300m.",
   "sources": [
    "https://datatech.disruptsmedia.com/data-centres/edgemode-agrees-eur300m-non-binding-sale-spain-data-centre-project",
    "https://www.expansion.com/empresas/2026/06/30/6a42a089468aeb9e1b8b457c.html"
   ]
  },
  {
   "date": "2026",
   "place": "Córdoba, Palma del Río, Vianos, Cáceres, Spain",
   "land_m2": null,
   "mw": null,
   "mw_basis": "per leased IT MW",
   "price_eur": null,
   "stage": "Land interests; staged to RTB and leasing",
   "status": "Non-binding term sheet",
   "buyer": "Pure DC",
   "seller": "EdgeMode",
   "note": "€1.5m per site upfront + €1.5m at RTB + €325,000 per MW of leased IT capacity.",
   "sources": [
    "https://bebeez.eu/2026/07/14/edgemode-looks-to-sell-multiple-data-center-development-sites-in-spain/",
    "https://data-central.co.uk/spanish-data-centre-land-starts-trading-like-power/"
   ]
  },
  {
   "date": "2026-06",
   "place": "Pori, Finland",
   "land_m2": 260000,
   "mw": null,
   "mw_basis": "secured grid capacity (MW not disclosed)",
   "price_eur": null,
   "stage": "Zoning, building permits and secured grid capacity",
   "status": "Agreed sale (price not disclosed)",
   "buyer": "Undisclosed European operator",
   "seller": "Polarnode",
   "note": "",
   "sources": [
    "https://data-central.co.uk/pori-turns-powered-land-into-a-sale/"
   ]
  },
  {
   "date": "2026-08",
   "place": "Milan area, Italy",
   "land_m2": 23000,
   "mw": 30,
   "mw_basis": "potential capacity (grid application submitted)",
   "price_eur": null,
   "stage": "Land secured; grid application filed",
   "status": "Acquired by developer (price not disclosed)",
   "buyer": "Magnora",
   "seller": "Not disclosed",
   "note": "Targeted for sale to a data center developer by 2027.",
   "sources": [
    "https://www.datacenterdynamics.com/en/news/magnora-acquires-land-outside-milan-italy-for-data-center-development/"
   ]
  }
 ]
}