By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below
Data center grid requests in Lombardy reached 44.96 GW by July 2026, 47% of the 95.86 GW requested across Italy, against national peak demand of about 58 GW: most will never be built. Italy now puts a data center and its connection into a single authorisation, and Lombardy’s 2026 law favours brownfield sites and sends projects over 10 MW to a regional conference. Sources (2)Key4bizKey4biz — la Lombardia chiede alla rete 44,96 GW↗
HLCHLC — Lombardy regional law on data centres (L.R. 11/2026)↗
What buyers ask for here
| Who | Where | Size | What they buy | Written |
|---|---|---|---|---|
| European developer | Italy (with Spain) | 10–30 MW | Sites to develop | Jul 2026 |
| Infrastructure fund | Italy and Spain | — | Powered sites | Jul 2026 |
| Global operator, EMEA acquisitions | Across EMEA | Large sites | Powered sites | Aug 2026 |
The first two rows come from July 2026 conversations being reconfirmed in writing. A seller’s agent has also offered a large ready-to-build project in Lombardy. Anonymised; stated requirements, not commitments to buy a specific site.
Where sites come from
Brownfield and regeneration areas, which Lombardy’s law favours with lower charges; for example a former steel site in Corsico now being built out by an operator. Sources (2)HLCHLC — Lombardy regional law on data centres (L.R. 11/2026)↗Pambianco Real EstatePambianco Real Estate — Marcegaglia sells Corsico industrial site to Retelit (Sep 2025)↗
How the power is won
Connection requests go to Terna, which issues a quote (STMG) within 90 days; the volume of requests far exceeds what will be built, so a credible, early request matters. Sources (3)TernaTerna — connection quote (STMG) procedure: quote within 90 days↗Terna LightboxTerna Lightbox — data centres and the transmission grid (300+ projects, 50+ GW)↗Key4bizKey4biz — la Lombardia chiede alla rete 44,96 GW↗
Planning and regulation
Decree-Law 21/2026 joins the data center and its grid connection in one authorisation and allows a temporary medium-voltage connection. Lombardy’s Law 11/2026 treats data centers over 5 MW as productive use and sends projects over 10 MW to a supra-municipal conference. HLC
Land and price benchmarks
Published Milan-area deals imply roughly 770 m² of land per MW (23,000 m² for about 30 MW). JLL notes capital broadening into Milan and Iberia. Sources (2)DCDDCD — Magnora acquires land outside Milan↗
JLLJLL — EMEA data centre report↗
Precedents in Italy
- Corsico, Milan: a steelmaker’s warehouses turned into a 13.6 MW data center — Under construction
Data and rules
Sources
Key4biz
HLCTerna LightboxTernaPambianco Real Estate
DCD
JLL
Last checked 2026-10-13. Aggregates and anonymised requirements only; no candidate site, owner or municipality is identified.