By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below
RWE obtained hybrid planning permission in July 2025 for a data campus on the demolished Didcot A coal plant site in Oxfordshire and completed its sale in November 2025. RWE’s annual report states the buyer paid £203 million, booked as a €225 million gain, for a 23-hectare restored site with a 300 MW grid connection and planning permission for a 200,000 m² data center. Analysts later named Amazon as the buyer. Sources (4)RWERWE — Annual Report 2025 (sale of a data centre development project, UK)↗
DCDDCD — RWE completes sale of planned Didcot data campus (Nov 2025)↗Energy VoiceEnergy Voice — RWE boosted by sale of UK coal power site to hyperscaler (Nov 2025)↗
DCDDCD — RWE sells Didcot A coal plant site to Amazon for data center (Dec 2025, citing analysts)↗
Timeline
| When | What happened |
|---|---|
| 2013 | Didcot A stops generating; later demolished. |
| Jul 2025 | Hybrid planning permission for the data campus. Delivering Didcot Data Campu |
| Nov 2025 | Sale completed: the buyer paid £203 million (RWE annual report). Sources (2) |
| Dec 2025 | Analysts name Amazon as the buyer. |
What changed between entry and exit
- Kept the site and its grid context after closure.
- Took the project through planning before selling.
Capital and counterparties
RWE (owner) to planning; the hyperscaler buys and builds.
Economics: confirmed and not disclosed
| Item | Figure | Note |
|---|---|---|
| Price paid by the buyer | £203 million | RWE Annual Report 2025 |
| Book gain for RWE | €225 million | Often misreported as the sale price Sources (2) |
| Site | 23 ha, fully restored | Former coal power station |
| Grid connection | 300 MW | Included in the sale |
| Price per grid MW | ≈£677,000 | £203m ÷ 300 MW (Ampervia calculation) |
| Entry price | Not applicable | Long-held utility land |
Risks and limitations
- Hyperscale size (300 MW): far above the sites most buyers ask Ampervia for.
- Early press reports gave €225 million as the price; that figure is RWE’s accounting gain, not what the buyer paid.
Relevance to Ampervia
Planning permission plus a grid-rich site is what a hyperscaler pays a premium for.
Sources
RWESources (2)
DCDDCD — RWE completes sale of planned Didcot data campus (Nov 2025)↗
DCDDCD — RWE sells Didcot A coal plant site to Amazon for data center (Dec 2025, citing analysts)↗Energy VoiceDelivering Didcot Data Campu
Last checked 2026-10-13. Third-party precedent, not an Ampervia project.