- Access and connection permit
- In Spain, the permiso de acceso y conexión: the operator’s grant of the right to connect a given load at a given node. Since RDL 7/2026 it carries a CNAE activity code.
- Access capacity
- The capacity, in MW, a network operator publishes as available at a node for new consumers (demand) or new plants (generation). In Spain it is published per node and compiled by the CNMC. See Spain grid capacity by province.
- AI factory
- Industry term for data centers built for AI training and inference, with much higher power density per rack than traditional facilities.
- AIFM
- Alternative investment fund manager, the regulated manager required under EU rules when capital is pooled from investors into a fund.
- Autoproducer unit
- In Irish rules, on-site or nearby dispatchable generation a data center must provide to cover its demand; required at 100% of MIC for sites of 1–10 MVA.
- Behind-the-meter power
- Generation on the consumer’s side of the grid meter (on-site gas, solar, batteries) supplying the data center directly.
- Brownfield site
- Previously developed land, often a closed factory. In Lombardy, brownfield data centers get lower construction charges than greenfield ones.
- Capacity reservation guarantee
- A deposit or periodic charge a developer pays to hold grid capacity before using it. Spain’s RDL 7/2026 created one for demand permits of 1 kV and above, payable until activity starts.
- Capex per MW
- Construction cost divided by IT capacity, the standard way to compare data center build costs.
- Club deal
- A transaction in which a small group of investors invest together, usually through an SPV, instead of through a blind-pool fund.
- CNAE code
- Spain’s classification of economic activities. Under RDL 7/2026 a demand permit states the CNAE code of the activity it will serve, and the permit lapses if the connected site does not keep that activity for three years.
- CNAE lock
- Shorthand for the RDL 7/2026 rule tying a Spanish demand permit to its declared activity code, which stops a factory’s permit being reused for a data center.
- Co-investment
- Investing directly in a specific deal alongside a sponsor or fund, usually on the same terms.
- Colocation
- A data center that leases space, power and cooling to several customers.
- Connection offer
- The operator’s formal offer setting the capacity, works, cost and date of a connection. The strongest evidence that a site is powered.
- Connection queue
- The list of pending connection requests an operator processes. Queue position, not land, often decides when a site can energise.
- Distribution grid
- The lower-voltage network run by distribution operators (in Spain, distributors such as i-DE, e-distribución or UFD). Most connections of a few to a few tens of MW sit here.
- DSO
- Distribution system operator: the company running the local lower-voltage grid.
- Edge data center
- A small facility, often under 5 MW, placed close to users for low latency.
- Energisation
- The moment a connection is switched on and the site can draw power.
- Firm connection
- A connection with guaranteed capacity at all times.
- FLAP-D
- Frankfurt, London, Amsterdam, Paris and Dublin, Europe’s five primary data center markets, all power-constrained. See FLAP-D connection thresholds.
- GDV
- Gross development value: the expected value of a project once built and let.
- Greenfield site
- Land never developed before, typically agricultural.
- Grid capacity (site)
- The total power a site may draw from the grid, including cooling and losses. Higher than the IT load; the ratio depends on PUE.
- Hyperscale
- Very large data centers built by or for the biggest cloud providers, usually tens to hundreds of MW per campus.
- IT load
- The power drawn by the servers and network equipment, excluding cooling and losses. Data center capacity and prices per MW usually refer to IT MW.
- Land option
- A contract giving the right, not the obligation, to buy land at an agreed price within a period, so a developer can secure power and permits before buying.
- MIC
- Maximum import capacity: in Ireland, the contracted maximum a site may draw from the grid. Irish data center rules are tiered by MIC.
- MVA
- Megavolt-ampere, the unit of apparent power used for connection sizes. Close to MW for planning purposes; connection rules in Berlin, Amsterdam, Dublin and London are set in MVA.
- Node
- A point on the grid, usually a substation busbar at one voltage, where capacity is published and new connections are made.
- Non-firm (flexible) connection
- A connection the operator may curtail at times of grid stress, offered sooner than a firm connection. Used in Germany, the UK and Ireland to connect loads earlier.
- Powered land
- Land with a grid connection, or a secured right to one, large enough for a data center. Its price is driven by the megawatts it can draw, so it is usually quoted per MW rather than per square metre. See What is powered land?
- Powered shell
- A building with power delivered to it but without the tenant’s fit-out (cooling, racks, internal electrical). A step after powered land.
- Pro-rata allocation
- Sharing scarce capacity among applicants in proportion to their requests, instead of first come, first served. Used by Frankfurt’s and Berlin’s grid operators.
- PUE
- Power usage effectiveness: total facility energy divided by IT energy. A PUE of 1.3 means 30% on top of the IT load.
- Ready-to-build (RTB)
- A data center site with land control, a grid connection offer or permit, and the planning permits needed to start construction. See What is a ready-to-build site?
- Shovel-ready
- Informal synonym for ready-to-build: construction could begin without further permits.
- Single authorisation (Italy)
- The single procedure introduced by Italy’s Decree-Law 21/2026, article 8, covering a data center and its grid connection in one authorisation.
- SPV
- Special purpose vehicle: a company formed to hold one project, so its investors, debt and risks stay separate. See How SPVs and club deals work.
- Substation
- A facility that transforms voltage between grid levels. Distance to a substation with spare capacity is one of the first site-selection filters.
- Transmission grid
- The high-voltage network run by the transmission system operator (Red Eléctrica in Spain, Terna in Italy, RTE in France). Large campuses connect here.
- TSO
- Transmission system operator: the company running the high-voltage grid of a country or zone.
- Will-serve letter
- A utility’s written statement that it can supply a site. Common in the US; in Europe the equivalent evidence is a connection offer or permit.