By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
It depends on the market, how firm the power is, and whether the figure is per grid MW or per IT MW. Completed sales include about €440,000 per grid MW near Madrid (2024) and about £677,000 per grid MW at Didcot, UK (2025). Market estimates run from about €512,000 per MW in tertiary markets to €2.26 million per MW in prime FLAP-D hubs (JLL, 2026). Sources (4)JLLJLL — EMEA data centre report↗
Noah IntelligenceNoah Intelligence — Europe’s data-centre land rush↗
ActivumSGActivumSG — €11m powered land sale to Pure DC↗
DCDDCD — DAMAC’s Edgnex to develop 40 MW data center in Madrid↗
Key facts
- Meco, Madrid (2024): €11 million for 25 MW of grid power, about €440,000 per grid MW. Completed sale (ActivumSG).
- Didcot, UK (2025): £203 million for a 23 ha site with a 300 MW grid connection, about £677,000 per grid MW. Completed sale (RWE Annual Report 2025).
- Prime FLAP-D powered land: €2.26 million per MW, 2026. Market estimate (JLL).
- Secondary and tertiary markets: €978,000 and €512,000 per MW. Market estimates (Noah Intelligence).
- Malpica, Toledo (2026): €1 million per MW of certified ready-to-build IT capacity. Non-binding offer.
- Per-MW figures above are Ampervia divisions of published prices and capacities; grid MW and IT MW are not interchangeable.
| Where | Date | Type | Capacity basis | Price per MW | Stage |
|---|---|---|---|---|---|
| Meco, Madrid | 2024 | Completed sale | Grid MW (25) | ≈€440,000 | Powered land: power agreement and dual feed |
| Didcot, UK | 2025 | Completed sale | Grid MW (300) | ≈£677,000 | Restored site, grid connection, planning permission |
| Malpica, Toledo | 2026 | Non-binding offer | IT MW at RTB | €1,000,000 | Payable when ready-to-build is certified |
| Prime FLAP-D hubs | 2026 | Market estimate (JLL) | Per MW | €2,260,000 | Powered land |
| Secondary markets | 2026 | Market estimate | Per MW | €978,000 | Powered land |
| Tertiary markets | 2026 | Market estimate | Per MW | €512,000 | Powered land |
What moves the price
- Firmness of power: an energised or permitted connection is worth several times a capacity that is only published.
- Market: primary hubs command a premium for latency and ecosystem.
- Timing: late power (years away) is discounted heavily.
- Transferability: rules like Spain’s CNAE lock can stop a permit following the land.
Questions
Is the price per IT MW or grid MW?
Why are Spanish prices lower than Frankfurt’s?