Home / Answers / Powered land price per MW

How much does powered land cost per MW in Europe?

It depends on the market, how firm the power is, and whether the figure is per grid MW or per IT MW.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

It depends on the market, how firm the power is, and whether the figure is per grid MW or per IT MW. Completed sales include about €440,000 per grid MW near Madrid (2024) and about £677,000 per grid MW at Didcot, UK (2025). Market estimates run from about €512,000 per MW in tertiary markets to €2.26 million per MW in prime FLAP-D hubs (JLL, 2026).

Key facts

  • Meco, Madrid (2024): €11 million for 25 MW of grid power, about €440,000 per grid MW. Completed sale (ActivumSG).
  • Didcot, UK (2025): £203 million for a 23 ha site with a 300 MW grid connection, about £677,000 per grid MW. Completed sale (RWE Annual Report 2025).
  • Prime FLAP-D powered land: €2.26 million per MW, 2026. Market estimate (JLL).
  • Secondary and tertiary markets: €978,000 and €512,000 per MW. Market estimates (Noah Intelligence).
  • Malpica, Toledo (2026): €1 million per MW of certified ready-to-build IT capacity. Non-binding offer.
  • Per-MW figures above are Ampervia divisions of published prices and capacities; grid MW and IT MW are not interchangeable.
Powered-land prices per MW: what each figure is
WhereDateTypeCapacity basisPrice per MWStage
Meco, Madrid2024Completed saleGrid MW (25)≈€440,000Powered land: power agreement and dual feed
Didcot, UK2025Completed saleGrid MW (300)≈£677,000Restored site, grid connection, planning permission
Malpica, Toledo2026Non-binding offerIT MW at RTB€1,000,000Payable when ready-to-build is certified
Prime FLAP-D hubs2026Market estimate (JLL)Per MW€2,260,000Powered land
Secondary markets2026Market estimatePer MW€978,000Powered land
Tertiary markets2026Market estimatePer MW€512,000Powered land

What moves the price

  • Firmness of power: an energised or permitted connection is worth several times a capacity that is only published.
  • Market: primary hubs command a premium for latency and ecosystem.
  • Timing: late power (years away) is discounted heavily.
  • Transferability: rules like Spain’s CNAE lock can stop a permit following the land.

Questions

Is the price per IT MW or grid MW?
Usually per IT MW in market reports, but deal announcements often quote grid MW. Check before comparing.
Why are Spanish prices lower than Frankfurt’s?
Lower land values, a younger market and more grid capacity outside Madrid. The gap narrows where power is scarce.

Sources

JLLNoah IntelligenceActivumSGDCDBeBeezRWEEdgeMode

Terms on this page: Powered land · Ready-to-build (RTB) · IT load · Grid capacity (site)

Related

All answers →

Looking for powered land in Europe?

Start with the Ampervia Powered-Land Map: candidate sites across six European countries, checked against public records, at zone level, free to explore.