Maintal, Frankfurt-Hanau: a business park sold to a data center developer for €40.1 million

Land and power assembled, then sold to an operator.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below

Quick answer

Listed landlord Sirius Real Estate bought the Maintal technology park, between Frankfurt and Hanau, in 2006 (DCD reports about €17 million). In November 2023 it notarised the sale of the park for €40.1 million, about 6% above its last book value; DCD reported the buyer as a data center developer, and local press later named EdgeConneX, which plans a data center there by the end of 2027.

Timeline

WhenWhat happened
Oct 2006Sirius acquires the Maintal technology park (DCD reports about €17m).
Before saleAnchor tenant leaves; DCD reports a change of use was pursued. DCD
Nov 2023Sale notarised at €40.1m, 5.7% net initial yield, ~6% above last book value (Sirius).
2025Local press: EdgeConneX bought the former Sirius Business Park and plans a data center by end-2027. Hanauer Anzeiger

What changed between entry and exit

  • Held an ordinary business park inside the Frankfurt–Hanau data center belt.
  • After the tenant left, sold to a buyer that valued it as a data center site rather than re-letting it.

Capital and counterparties

Sirius held the asset for 17 years; the developer funds the data center.

Economics: confirmed and not disclosed

ItemFigureNote
Entry price (2006)≈€17 millionAs reported by DCD; single source DCD
Exit price (Nov 2023)€40.1 millionNotarised sale (Sirius)
Versus last book value≈+6%Sirius statement UKREiiF
Versus 2006 price≈2.4× grossBefore 17 years of capex and costs; not a net return

Risks and limitations

  • The 2006 price and the 37,830 m² site area come from one press source (DCD).
  • Holding costs and capex are not public; most of the uplift had already been booked over time.

Relevance to Ampervia

A business park in an established cluster (Frankfurt–Hanau) sold to a data center developer at a premium to book. Location in the cluster is what the buyer paid for; the sources do not describe the power arrangements.

Sources

Europe Real EstateUKREiiFDCDImmobilien ZeitungHanauer Anzeiger

Last checked 2026-10-13. Third-party precedent, not an Ampervia project.