Meco, Madrid: industrial plot to 25 MW powered land, sold for €11 million

Land and power assembled, then sold to an operator.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below

Quick answer

A private equity manager (ActivumSG) bought a 17,650 m² plot in Meco, on the Madrid–Barcelona corridor, from two local manufacturers in July 2021, secured a 25 MW power agreement in 2022 and a dual feed in 2023, then sold it to data center operator Pure DC for €11 million in July 2024. Pure DC won final planning approval in November 2025 for a €400 million first phase (30 MW and a private substation) of a 70 MW campus.

Timeline

WhenWhat happened
Jul 2021ActivumSG buys the plot from two local manufacturing companies (price not disclosed). ActivumSG
202225 MW power agreement secured. ActivumSG
2023Dual power feed secured. ActivumSG
Jul 2024Sold to Pure DC for €11 million (about €440,000 per grid MW).
Nov 2025Pure DC receives final planning approval: €400m Phase 1, 30 MW plus private substation; campus planned at 70 MW.

What changed between entry and exit

  • Picked an industrial plot on an established logistics corridor rather than waiting for a listed site.
  • Secured the power agreement, then redundancy (dual feed): the step operators pay for.
  • Sold at the point an operator could take over planning and build.

Capital and counterparties

ActivumSG Fund VI held the land through the power phase. Pure DC (backed by Oaktree) bought it and funds the build.

Economics: confirmed and not disclosed

ItemFigureNote
Entry price (2021)Not disclosedTwo manufacturers sold the plot
Comparable land value (estimate)≈€1.5–3.5 millionAmpervia estimate, not the actual price: 17,650 m² at €85/m² (Meco logistics land sold in bulk, Nov 2022) to ≈€182–200/m² (Meco industrial plots listed for sale). Excludes any buildings on the plot.
Exit price (2024)€11 millionCompleted sale
Exit per grid MW≈€440,000€11m ÷ 25 MW (Ampervia calculation)
Buyer’s first-phase investment€400 millionPure DC’s build cost, not seller proceeds Pure DC

Risks and limitations

  • The entry price is not public, so the seller’s profit cannot be calculated. Comparable Meco land suggests the plot was worth roughly €1.5–3.5 million as industrial land, which would put the €11 million exit at about 3–7× land value: an estimate, before holding and power costs.
  • Power came through an agreement secured before RDL 7/2026 tied Spanish permits to a declared activity.

Relevance to Ampervia

The value step was power, not land: an industrial plot with a 25 MW agreement became a site an operator would buy. This is the core of Ampervia’s phase 1.

Sources

ActivumSGPropertyEUDCDEjePrimeNavekoBGM Naves Industriales

Last checked 2026-10-13. Third-party precedent, not an Ampervia project.