By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
An investor funds the early steps that turn a plot into a powered, permitted site: an option on the land, the grid request, studies and permits. Value is created when capacity is confirmed and when the site reaches ready-to-build, as staged deals show (€1.5 million per site upfront plus €1.5 million at RTB in one Spanish term sheet). It fails when the grid answer is no, permits stall, or no buyer pays for the stage reached. Sources (4)BeBeezBeBeez — EdgeMode looks to sell data center development sites in Spain↗DataTechDataTech — EdgeMode agrees €300m non-binding sale of Spain project↗
ActivumSGActivumSG — €11m powered land sale to Pure DC↗
BOEBOE — Real Decreto-ley 7/2026↗
Key facts
- Staged pricing example: €1.5m per site upfront, €1.5m at RTB and €325,000 per MW of leased IT capacity (non-binding, Spain; BeBeez).
- RTB-linked pricing example: €1m per MW of certified RTB IT capacity, payable only at closing (non-binding; DataTech).
- Completed powered-land sale near Madrid: 17,650 m² with a 25 MW power agreement for €11m (ActivumSG).
- In Spain, the request must be filed as a data center from the start: permits carry a CNAE code and lapse if the activity changes within three years (BOE).
| Step | Spend | Value created | Failure mode |
|---|---|---|---|
| Option the land | Option premium | Exclusive control | Owner will not sign; price too high |
| File the grid request | Studies, fees, guarantees | A place in the queue | No capacity; long delay |
| Connection offer | Reservation charges | Capacity reserved | Cost of works too high |
| Permits | Design, legal | Ready-to-build | Planning refused or delayed |
| Sale or build | — | Exit at the stage reached | No buyer at the expected price |
Capital needed
Early steps cost far less than the land and a fraction of the build. Banks usually lend against land value, not against studies or grid fees, so the early steps are funded with equity, seller options or staged payments from a buyer.
Fallback if it fails
Under an option, a failed grid answer costs the premium and studies, not the land price. Once land is bought, a failed permit leaves industrial land that can be resold, not necessarily at cost.
Questions
Is powered land a yielding investment?
What evidence proves a site is powered?
Sources
- BeBeez — EdgeMode looks to sell data center development sites in Spain
- DataTech — EdgeMode agrees €300m non-binding sale of Spain project
- ActivumSG — €11m powered land sale to Pure DC
- BOE — Real Decreto-ley 7/2026
Terms on this page: Powered land · Land option · Connection offer · Ready-to-build (RTB) · CNAE lock