Quick answer

Frankfurt had about 997 MW of data center capacity and 4% vacancy in mid-2026, and a new grid connection of 50 MW or more in the Rhine-Main area can take up to 13 years. Growth is moving to Berlin, Cologne/Düsseldorf and Munich. Near Frankfurt, land ready for a data center trades at €1,000–2,000+/m², against about €350/m² for industrial plots.

997 MWFrankfurt installed, 4% vacancy (JLL, Jun 2026) JLL study via AssetPhysics
Up to 13 yrsgrid wait for 50 MW+ in Rhine-Main tz.de
€1,000–2,000+per m² for data-center-ready land near Frankfurt, vs ≈€350 industrial Cash.
643 MWplanned in Berlin, on 136 MW installed JLL study via AssetPhysics

What buyers ask for here

WhoWhereSizeWhat they buyWritten
Infrastructure fundDüsseldorf, Cologne, Berlin5–15 MWPowered land, greenfield or brownfieldJul 2026
European operator, development teamGermany (with UK, France)≥40 MVA in Tier 1–2 markets; ≥200 MVA elsewhereBrownfieldJul 2026
European operator, M&A teamFrankfurt (with London, Paris)~100 MVA ideal; smaller only inside established clustersBrownfieldJul 2026
Global operator, EMEA acquisitionsAcross EMEALarge sitesPowered sitesAug 2026

Germany appears in all four written buyer briefs Ampervia holds. A DACH powered-land developer has also offered sites to our buyers. Anonymised; stated requirements, not commitments to buy a specific site.

Main metros

MetroInstalledUnder construction or plannedSource
Frankfurt997 MWFrankfurt market at 4% vacancyJLL, Jun 2026
Berlin136 MW74 MW under construction, 643 MW plannedJLL, Jun 2026
Munich102 MW122 MW plannedJLL, Jun 2026
Cologne / Düsseldorf55 MW100 MW plannedJLL, Jun 2026

Where sites come from

Business parks, industrial plots and former power-plant sites. Frankfurt-area projects are moving further out: new schemes are increasingly planned about 40 km from the city centre. German Business Review

How the power is won

Since April 2026 the four transmission operators allocate large connections by project maturity, with secured land among the criteria, instead of first come, first served. Berlin rations new data center connections of 3.5 MVA and above through an allocation procedure. In Rhine-Main, demand for connections far exceeds what the upstream grid can supply.

Planning and regulation

The Energy Efficiency Act (EnEfG) requires new data centers to reach a PUE of 1.2; the June 2026 cabinet amendment gives four years instead of two to get there, and makes waste-heat reuse mandatory only where a heat network is available. Some municipalities around Frankfurt refuse data centers over power use and low local tax income.

Land and price benchmarks

Colliers puts data-center land near Frankfurt mostly at €1,000–2,000+/m², with top plots up to €3,500/m² reported, against about €350/m² for industrial and logistics land. The drivers are power within five years, a cloud availability zone and permission to build multi-storey. Data center transactions reached about €1.2 billion in 2025.

Precedents in Germany

Data and rules

Sources

JLL study via AssetPhysicstz.deCash.German Business ReviewGerman TSOsRaueBMWEFPS LawHandelsblatt

Last checked 2026-10-13. Aggregates and anonymised requirements only; no candidate site, owner or municipality is identified.