Corsico, Milan: a steelmaker’s warehouses turned into a 13.6 MW data center

Brownfield redevelopment, then build and operate.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below

Quick answer

Steel group Marcegaglia sold an industrial complex in Corsico, on Milan’s western ring road, to telecom operator Retelit (announced September 2025). The site had two warehouses of about 11,500 m², offices and a yard, with high-capacity electrical and data connections already in place. Retelit broke ground in 2026 on a 13.6 MW data center in two buildings, with first capacity targeted for 2027.

Timeline

WhenWhat happened
Before 2025Part of a Marcegaglia steel site: two warehouses (~11,500 m²), ~600 m² offices, ~6,000 m² yard. Pambianco Real Estate
Sep 2025Sale to Retelit announced (price not disclosed).
2026Construction starts: two buildings, 13.6 MW total. Retelit
2027First capacity targeted. Retelit

What changed between entry and exit

  • Chose an existing industrial site with power and fibre close to Milan.
  • The operator bought and builds itself: no intermediate developer.

Capital and counterparties

Retelit funds land and build within a €350m three-year investment plan.

Economics: confirmed and not disclosed

ItemFigureNote
Purchase priceNot disclosed
Comparable value (estimate)≈€10–15 million at asking levelsAmpervia estimate, not the actual price: ≈12,100 m² of warehouses and offices at €800–1,200/m², the range quoted for Corsico warehouses in good condition. Older industrial space usually trades below that. Vendiamo Imprese
Capacity13.6 MWTwo buildings Retelit
Operator investment plan€350m over three yearsGroup-wide, not this site alone

Risks and limitations

  • No price disclosed.
  • Lombardy has very large connection queues (44.96 GW of data center requests); an existing connection shortens the path.

Relevance to Ampervia

In Milan, existing industrial connections close to the city are what operators buy. Lombardy’s new law also rewards brownfield sites with lower construction charges.

Sources

Pambianco Real EstateWorld CapitalRetelitKey4bizVendiamo Imprese

Last checked 2026-10-13. Third-party precedent, not an Ampervia project.