By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below
German developer AVENTOS contractually secured a 63 MVA grid connection for a ~28,400 m² plot next to its LUXWERK business campus in Berlin-Siemensstadt, 500 m from the NTT internet exchange, then sold it in a structured process to Tristan Capital Partners’ EPISO 6 fund (announced 4 December 2025). The plans show three three-storey data center buildings, a substation and a reception building. The price was kept confidential. Sources (3)AVENTOS press releaseAVENTOS press release — sale of data center plot in Berlin to Tristan Capital Partners (4 Dec 2025, PDF)↗Immobilien ZeitungImmobilien Zeitung — Tristan buys about 3 ha for data centers in Berlin-Siemensstadt (4 Dec 2025)↗DCDDCD — Aventos sells planned data center site in Berlin to Tristan Capital Partners (Dec 2025)↗
Timeline
| When | What happened |
|---|---|
| Before sale | AVENTOS contractually secures a 63 MVA connection for the plot (grid connection contract in place). AVENTOS press release |
| 4 Dec 2025 | Sale to Tristan Capital Partners’ EPISO 6 fund announced after a structured sale process; price confidential. Sources (2)AVENTOS press releaseAVENTOS press release — sale of data center plot in Berlin to Tristan Capital Partners (4 Dec 2025, PDF)↗ |
| Plans | Three three-storey data center buildings, a substation and a reception building; waste heat to warm the neighbouring LUXWERK campus. Sources (2)AVENTOS press releaseAVENTOS press release — sale of data center plot in Berlin to Tristan Capital Partners (4 Dec 2025, PDF)↗Immobilien ZeitungImmobilien Zeitung — Tristan buys about 3 ha for data centers in Berlin-Siemensstadt (4 Dec 2025)↗ |
What changed between entry and exit
- Secured the grid connection contract (63 MVA), which the seller calls “a crucial milestone in the value chain”.
- Prepared plans for three buildings and a substation.
- Ran a structured sale to institutional buyers instead of building.
Capital and counterparties
AVENTOS (developer) to the grid-contract milestone; Tristan Capital Partners’ EPISO 6 fund for the next stage. Advisers: Greenberg Traurig and ATC Tax (seller), Clifford Chance (buyer).
Economics: confirmed and not disclosed
| Item | Figure | Note |
|---|---|---|
| Entry price | Not disclosed | |
| Exit price (2025) | Confidential | Per the seller’s press release AVENTOS press release |
| Grid connection | 63 MVA, contracted | Before the sale AVENTOS press release |
| Plot | ≈28,400 m² | AVENTOS press release |
Risks and limitations
- No prices are public, so the uplift cannot be measured.
- Berlin rations large connections through an annual allocation; a contract already in hand is what made the plot sellable.
Relevance to Ampervia
In a rationed grid like Berlin’s, the signed grid contract is the asset. An institutional fund bought at that milestone, before any building.
Sources
AVENTOS press releaseImmobilien ZeitungDCD
Last checked 2026-10-13. Third-party precedent, not an Ampervia project.