Home / Case studies / Malpica, Toledo

Malpica, Toledo: leased land priced at €1 million per ready-to-build MW

Partner enters before ready-to-build.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below

Quick answer

EdgeMode controls about 105 ha near Mora (Toledo) through a 35-year lease at €2,000 per hectare per year (SEC filing) for a 300 MW project. In June 2026 Spark AI Foundry signed a non-binding offer to buy the project company once it reaches ready-to-build, at €1 million per MW of certified RTB IT capacity (up to €300 million). The buyer would then need roughly €3 billion to build. Nothing is binding yet.

Timeline

WhenWhat happened
Lease≈105.26 ha leased for 35 years at €2,000/ha/yr (SEC exhibit).
Dec 2025Environmental authorisation submitted.
24 Jun 2026Non-binding offer from Spark AI Foundry: €1m per RTB IT MW, up to €300m, payable at closing once RTB is certified.
Jul 2026Separately, Pure DC term sheet for EdgeMode’s other Spanish sites: €1.5m per site upfront, €1.5m at RTB, €325,000 per leased MW, with an option to reinvest through a JV.
End 2026 / Q1 2027Ready-to-build expected; long-stop date applies.

What changed between entry and exit

  • Controlled a large plot with a lease instead of a purchase, keeping early cash low.
  • Pursued environmental authorisation and building permit to reach RTB.
  • Agreed the price formula with a buyer before RTB: the buyer is in, conditionally, before completion.

Capital and counterparties

EdgeMode funds the path to RTB; the buyer pays at RTB and funds the build. In the Pure DC term sheet, payments are staged by milestone.

Economics: confirmed and not disclosed

ItemFigureNote
Land control cost≈€210,000 a year105 ha × €2,000/ha (Ampervia calculation)
Offer at RTB€1m per RTB IT MW, up to €300mNon-binding
Staged terms (other sites)€1.5m upfront + €1.5m at RTB + €325k per leased MWNon-binding term sheet

Risks and limitations

  • Both deals are non-binding and subject to due diligence and permits.
  • The price is per certified RTB MW: if permits or grid fall short, the value falls with them.
  • Spending on studies, permits and grid works is not disclosed.

Relevance to Ampervia

A buyer can commit before RTB, with payment tied to milestones. That is the model Ampervia uses: members fund the early steps, a partner pays at agreed gates.

Sources

Last checked 2026-10-13. Third-party precedent, not an Ampervia project.

All case studies → · Deals dataset →