By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
816 of 6,186 Spanish distribution nodes publish any available demand capacity in the CNMC’s August 2026 data, and only 104 offer 20 MW or more, Ampervia’s screening threshold for a data center site. Open nodes fell from 862 in June 2026. Province table below, updated monthly. CNMC
Download this dataset: JSON · CSV · Markdown — CC BY 4.0, attribution to Ampervia
Findings
Of 6,186 distribution nodes, 200 publish 10 MW or more and 104 publish 20 MW or more of demand capacity (August 2026).
862 nodes published capacity in June 2026; 816 in August 2026.
Only 9 Madrid nodes offer 20 MW or more, and none of its 91 Red Eléctrica transmission nodes shows demand capacity.
It shows where a request can be filed. Only the operator’s study confirms capacity for a specific project.
Province table
| Province | Distribution nodes | Nodes with demand capacity | Nodes ≥10 MW | Nodes ≥20 MW | Available demand capacity (MW) | Largest node (MW) | Change in open nodes since June 2026 |
|---|---|---|---|---|---|---|---|
| Lugo | 57 | 37 | 21 | 13 | 1,074.6 | 100 | -1 |
| Madrid | 587 | 95 | 28 | 9 | 743.8 | 29.8 | -7 |
| Murcia | 166 | 27 | 21 | 13 | 593.7 | 69.2 | +2 |
| Valencia/València | 230 | 25 | 14 | 9 | 480.6 | 60.8 | -6 |
| Asturias | 203 | 118 | 1 | 1 | 450.3 | 100 | +3 |
| Barcelona | 184 | 22 | 13 | 6 | 386.6 | 96.6 | +1 |
| Sevilla | 207 | 24 | 14 | 8 | 330.6 | 35.9 | +2 |
| Balears, Illes | 48 | 26 | 12 | 5 | 305.2 | 31.8 | +1 |
| Palmas, Las | 27 | 19 | 7 | 2 | 199.1 | 30.4 | +2 |
| Cádiz | 166 | 26 | 9 | 1 | 190.9 | 32.4 | +0 |
| Cáceres | 167 | 36 | 5 | 2 | 188.3 | 26 | -2 |
| Ourense | 46 | 26 | 4 | 4 | 179.9 | 70 | +0 |
| Granada | 86 | 21 | 3 | 0 | 159.7 | 14.2 | +0 |
| Zaragoza | 244 | 9 | 4 | 3 | 152.7 | 42.3 | +2 |
| Alicante/Alacant | 136 | 12 | 5 | 5 | 144.1 | 23.5 | -8 |
| Cantabria | 116 | 39 | 4 | 2 | 141.6 | 37 | +4 |
| Lleida | 74 | 4 | 4 | 3 | 135.8 | 73.7 | +0 |
| Pontevedra | 63 | 31 | 2 | 1 | 123.2 | 25.0 | -1 |
| Palencia | 65 | 12 | 4 | 2 | 110.8 | 30 | +1 |
| Huelva | 74 | 9 | 3 | 2 | 104.2 | 33.1 | +1 |
| Teruel | 90 | 12 | 5 | 0 | 102.0 | 17.2 | +1 |
| Almería | 72 | 4 | 3 | 2 | 100.6 | 63.2 | +0 |
| Soria | 68 | 4 | 3 | 3 | 98.0 | 40.1 | +0 |
| Coruña, A | 116 | 35 | 0 | 0 | 86.8 | 9.4 | -6 |
| Tarragona | 50 | 3 | 2 | 1 | 83.2 | 66.2 | +1 |
| Navarra | 249 | 5 | 2 | 2 | 56.8 | 28.8 | +2 |
| Cuenca | 76 | 4 | 2 | 1 | 54.1 | 27.1 | +0 |
| Santa Cruz de Tenerife | 20 | 4 | 2 | 2 | 50.8 | 24.4 | -1 |
| Córdoba | 86 | 1 | 1 | 1 | 46.4 | 46.4 | +0 |
| Ciudad Real | 106 | 49 | 0 | 0 | 45.2 | 4.0 | +0 |
| León | 150 | 28 | 0 | 0 | 34.9 | 6.2 | +0 |
| Zamora | 66 | 3 | 2 | 1 | 34.7 | 20.1 | -6 |
| Rioja, La | 127 | 4 | 0 | 0 | 20.7 | 9.7 | +0 |
| Castellón/Castelló | 84 | 5 | 0 | 0 | 15.3 | 8.5 | -2 |
| Ávila | 62 | 3 | 0 | 0 | 10.2 | 3.8 | +0 |
| Toledo | 131 | 14 | 0 | 0 | 9.7 | 1.8 | +0 |
| Badajoz | 159 | 4 | 0 | 0 | 7.7 | 4 | +0 |
| Jaén | 80 | 2 | 0 | 0 | 7.4 | 3.7 | +0 |
| Ceuta | 1 | 1 | 0 | 0 | 6.4 | 6.4 | +1 |
| Burgos | 131 | 2 | 0 | 0 | 4.2 | 2.1 | +2 |
| Girona | 87 | 4 | 0 | 0 | 2.8 | 0.7 | +0 |
| Huesca | 145 | 5 | 0 | 0 | 2.8 | 1 | +0 |
| Gipuzkoa | 204 | 1 | 0 | 0 | 1.3 | 1.3 | +0 |
| Segovia | 58 | 1 | 0 | 0 | 0.4 | 0.4 | -27 |
| Araba/Álava | 65 | 0 | 0 | 0 | 0 | 0 | +0 |
| Albacete | 88 | 0 | 0 | 0 | 0 | 0 | +0 |
| Guadalajara | 74 | 0 | 0 | 0 | 0 | 0 | +0 |
| Salamanca | 107 | 0 | 0 | 0 | 0 | 0 | +0 |
| Valladolid | 141 | 0 | 0 | 0 | 0 | 0 | -5 |
| Málaga | 116 | 0 | 0 | 0 | 0 | 0 | +0 |
| Bizkaia | 231 | 0 | 0 | 0 | 0 | 0 | +0 |
Method
Source: the CNMC’s national access-capacity service, layers Demanda en Distribución and Demanda en Transporte, publication period August 2026, pulled by Ampervia on 2026-10-12. Comparison period: June 2026.
- Distribution: each node’s published available capacity (CAP_DISPONIBLE, MW) for new demand, summed and counted by province.
- Transmission: a Red Eléctrica node is counted as showing demand capacity if any of its published demand categories is above zero.
- Province names are as published by the CNMC. Ampervia does not publish node or municipality detail.
- Published capacity is indicative and changes as permits are granted, lapse or are surrendered. Only the network operator can confirm capacity for a specific request.
Field dictionary
| Field | Meaning | Unit |
|---|---|---|
| province | Province name as published by the CNMC | text |
| dist_nodes | Distribution nodes published in the province | count |
| dist_open | Distribution nodes with available demand capacity above zero | count |
| dist_10 | Distribution nodes with 10 MW or more available | count |
| dist_20 | Distribution nodes with 20 MW or more available | count |
| dist_total | Sum of available demand capacity across the province’s distribution nodes | MW |
| dist_max | Largest single-node available capacity in the province | MW |
| prev_open | dist_open in the previous published period | count |
| prev_total | dist_total in the previous published period | MW |
| slug | URL slug of the province page on ampervia.com | text |
| tx_nodes | Red Eléctrica transmission nodes in the province | count |
| tx_open | Transmission nodes showing any demand capacity above zero | count |
How to reproduce these figures
- Open the CNMC’s national access-capacity map and select the publication period.
- Take the layers Demanda en Distribución and Demanda en Transporte.
- For distribution, read each node’s available capacity (CAP_DISPONIBLE, in MW) and group by province: count nodes, count those above 0, at or above 10 and at or above 20, sum the values and take the maximum.
- For transmission, count a node as open if any published demand category is above zero.
Limitations
- Province totals are not simultaneously usable capacity. Each figure is published per node; nodes can share upstream constraints, so the sum is an upper bound.
- Published capacity is indicative. It changes as permits are granted, lapse or are surrendered, and only the network operator can confirm capacity for a specific request.
- Available capacity does not mean a data center can obtain it: since RDL 7/2026 a request must state the activity, and congested transmission nodes are allocated by tender.
- The dataset stops at province level. Ampervia does not publish node or municipality detail.
Version history
- 2026-10-12: CNMC period August 2026.
- 2026-07-16: CNMC period June 2026 (first edition).