By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

In Cádiz, 26 of 166 distribution nodes (16%) publish available demand capacity, 190.9 MW in total (August 2026, CNMC). 9 offer 10 MW or more and 1 offer 20 MW or more; the largest single node shows 32.4 MW. CNMC

26 / 166nodes with demand capacity
1nodes ≥20 MW
190.9 MWavailable in total
10 / 51rank in Spain

Cádiz against Spain

MeasureCádizSpain
Distribution nodes1666,186
Nodes with demand capacity26816
Nodes ≥10 MW9200
Nodes ≥20 MW1104
Available demand capacity (MW)190.97,078.1
Largest node (MW)32.4—
Change in open nodes since June 2026+0-46
Transmission nodes with demand capacity8 of 18290 of 937

What this means for a data center

1 node in Cádiz publish 20 MW or more of demand capacity, at or above Ampervia’s 20 MW screening threshold for a data center site. Whether a specific request succeeds depends on the operator’s study, the site and the land.

Since March 2026, a Spanish demand access permit is tied to the CNAE activity code declared in the request (RDL 7/2026), so the request has to be filed as a data center from the start.

Method

Source: the CNMC’s national access-capacity service, layers Demanda en Distribución and Demanda en Transporte, publication period August 2026, pulled by Ampervia on 2026-10-12. Comparison period: June 2026.

  • Distribution: each node’s published available capacity (CAP_DISPONIBLE, MW) for new demand, summed and counted by province.
  • Transmission: a Red Eléctrica node is counted as showing demand capacity if any of its published demand categories is above zero.
  • Province names are as published by the CNMC. Ampervia does not publish node or municipality detail.
  • Published capacity is indicative and changes as permits are granted, lapse or are surrendered. Only the network operator can confirm capacity for a specific request.

Sources

CNMCBOE

Related

Looking for powered land in Europe?

Start with the Ampervia Powered-Land Map: candidate sites across six European countries, checked against public records, at zone level, free to explore.