By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
Along the A-2 Henares corridor, reported industrial land prices in mid-2026 were about €500/m² in Coslada, €400–450 in San Fernando de Henares, about €300 in Torrejón de Ardoz and €225–250 in Alcalá de Henares. Prices have risen 25–40% since the pandemic, with data centers and logistics competing for scarce plots. Sources (3)El DebateEl Debate — Radiografía del suelo industrial en Madrid (18 Jun 2026)↗
ABCABC — Escasez de suelo industrial y encarecimiento (17 Jun 2026)↗
ActivumSGActivumSG — €11m powered land sale to Pure DC↗
Key facts
- Coslada: around €500/m², with availability nearly exhausted (El Debate, June 2026).
- San Fernando de Henares: €400–450/m².
- Torrejón de Ardoz: about €300/m² (El Debate); ABC reports €400–450 for San Fernando and Torrejón together.
- Alcalá de Henares: €225–250/m².
- Southern Madrid, Villaverde: €450–500/m² (ABC).
- Industrial land is up 25–40% since the pandemic (ABC, June 2026).
| Area | €/m² | Source |
|---|---|---|
| Coslada | ≈500 | El Debate |
| San Fernando de Henares | 400–450 | El Debate |
| Torrejón de Ardoz | ≈300 (El Debate) · 400–450 (ABC) | El Debate, ABC |
| Alcalá de Henares | 225–250 | El Debate |
| Villaverde | 450–500 | ABC |
Land is the small part of the cost
At €300–500/m² and roughly 550–770 m² per MW, land works out at about €165,000–385,000 per MW before power. A secured connection is what multiplies the value: compare the €11 million paid for a 25 MW site in Meco.
Power is the constraint in Madrid
In the CNMC’s August 2026 data, 95 of Madrid’s 587 distribution nodes publish any demand capacity and only 9 offer 20 MW or more; no Red Eléctrica transmission node in the province shows demand capacity. See Madrid grid capacity.
Questions
Is cheaper land further out better?
Sources
Terms on this page: Powered land · Node