By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
In Santa Cruz de Tenerife, 4 of 20 distribution nodes (20%) publish available demand capacity, 50.8 MW in total (August 2026, CNMC). 2 offer 10 MW or more and 2 offer 20 MW or more; the largest single node shows 24.4 MW. CNMC
Santa Cruz de Tenerife against Spain
| Measure | Santa Cruz de Tenerife | Spain |
|---|---|---|
| Distribution nodes | 20 | 6,186 |
| Nodes with demand capacity | 4 | 816 |
| Nodes ≥10 MW | 2 | 200 |
| Nodes ≥20 MW | 2 | 104 |
| Available demand capacity (MW) | 50.8 | 7,078.1 |
| Largest node (MW) | 24.4 | — |
| Change in open nodes since June 2026 | -1 | -46 |
| Transmission nodes with demand capacity | 13 of 43 | 290 of 937 |
What this means for a data center
2 nodes in Santa Cruz de Tenerife publish 20 MW or more of demand capacity, at or above Ampervia’s 20 MW screening threshold for a data center site. Whether a specific request succeeds depends on the operator’s study, the site and the land.
Since March 2026, a Spanish demand access permit is tied to the CNAE activity code declared in the request (RDL 7/2026), so the request has to be filed as a data center from the start.
Method
Source: the CNMC’s national access-capacity service, layers Demanda en Distribución and Demanda en Transporte, publication period August 2026, pulled by Ampervia on 2026-10-12. Comparison period: June 2026.
- Distribution: each node’s published available capacity (CAP_DISPONIBLE, MW) for new demand, summed and counted by province.
- Transmission: a Red Eléctrica node is counted as showing demand capacity if any of its published demand categories is above zero.
- Province names are as published by the CNMC. Ampervia does not publish node or municipality detail.
- Published capacity is indicative and changes as permits are granted, lapse or are surrendered. Only the network operator can confirm capacity for a specific request.