Spain grid data updated: CNMC August 2026 period, 51 provincesSee the province table →
Spain grid data: August 2026 →
Home / Data / Spain grid capacity / Tarragona

Grid capacity for data centers in Tarragona

Published demand capacity on Tarragona’s distribution grid, rank 25 of 51 provinces. CNMC period August 2026.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

In Tarragona, 3 of 50 distribution nodes (6%) publish available demand capacity, 83.2 MW in total (August 2026, CNMC). 2 offer 10 MW or more and 1 offer 20 MW or more; the largest single node shows 66.2 MW. CNMC

3 / 50nodes with demand capacity
1nodes ≥20 MW
83.2 MWavailable in total
25 / 51rank in Spain

Tarragona against Spain

MeasureTarragonaSpain
Distribution nodes506,186
Nodes with demand capacity3816
Nodes ≥10 MW2200
Nodes ≥20 MW1104
Available demand capacity (MW)83.27,078.1
Largest node (MW)66.2—
Change in open nodes since June 2026+1-46
Transmission nodes with demand capacity0 of 22290 of 937

What this means for a data center

1 node in Tarragona publish 20 MW or more of demand capacity, enough in principle for a small data center (roughly 10–20 MW of grid capacity). Whether a specific request succeeds depends on the operator’s study, the site and the land.

Since March 2026, a Spanish demand access permit is tied to the CNAE activity code declared in the request (RDL 7/2026), so the request has to be filed as a data center from the start.

Method

Source: the CNMC’s national access-capacity service, layers Demanda en Distribución and Demanda en Transporte, publication period August 2026, pulled by Ampervia on 2026-10-12. Comparison period: June 2026.

  • Distribution: each node’s published available capacity (CAP_DISPONIBLE, MW) for new demand, summed and counted by province.
  • Transmission: a Red Eléctrica node is counted as showing demand capacity if any of its published demand categories is above zero.
  • Province names are as published by the CNMC. Ampervia does not publish node or municipality detail.
  • Published capacity is indicative and changes as permits are granted, lapse or are surrendered. Only the network operator can confirm capacity for a specific request.

Sources

Related

Looking for powered land in Europe?

Start with the Ampervia Powered-Land Map: verified powered-land sites across seven European countries, redacted to zone level, free to explore.