By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

In Teruel, 12 of 90 distribution nodes (13%) publish available demand capacity, 102.0 MW in total (August 2026, CNMC). 5 offer 10 MW or more and 0 offer 20 MW or more; the largest single node shows 17.2 MW. CNMC

12 / 90nodes with demand capacity
0nodes ≥20 MW
102.0 MWavailable in total
21 / 51rank in Spain

Teruel against Spain

MeasureTeruelSpain
Distribution nodes906,186
Nodes with demand capacity12816
Nodes ≥10 MW5200
Nodes ≥20 MW0104
Available demand capacity (MW)102.07,078.1
Largest node (MW)17.2—
Change in open nodes since June 2026+1-46
Transmission nodes with demand capacity0 of 10290 of 937

What this means for a data center

No node in Teruel publishes 20 MW or more, but 5 publish 10 MW or more: enough for an edge or small enterprise data center, not for a 20 MW-plus build without reinforcement or a transmission connection.

Since March 2026, a Spanish demand access permit is tied to the CNAE activity code declared in the request (RDL 7/2026), so the request has to be filed as a data center from the start.

Method

Source: the CNMC’s national access-capacity service, layers Demanda en Distribución and Demanda en Transporte, publication period August 2026, pulled by Ampervia on 2026-10-12. Comparison period: June 2026.

  • Distribution: each node’s published available capacity (CAP_DISPONIBLE, MW) for new demand, summed and counted by province.
  • Transmission: a Red Eléctrica node is counted as showing demand capacity if any of its published demand categories is above zero.
  • Province names are as published by the CNMC. Ampervia does not publish node or municipality detail.
  • Published capacity is indicative and changes as permits are granted, lapse or are surrendered. Only the network operator can confirm capacity for a specific request.

Sources

CNMCBOE