Grid capacity for data centers in Palmas, Las

Published demand capacity on Palmas, Las’s distribution grid, rank 9 of 51 provinces. CNMC period August 2026.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

In Palmas, Las, 19 of 27 distribution nodes (70%) publish available demand capacity, 199.1 MW in total (August 2026, CNMC). 7 offer 10 MW or more and 2 offer 20 MW or more; the largest single node shows 30.4 MW. CNMC

19 / 27nodes with demand capacity
2nodes ≥20 MW
199.1 MWavailable in total
9 / 51rank in Spain

Palmas, Las against Spain

MeasurePalmas, LasSpain
Distribution nodes276,186
Nodes with demand capacity19816
Nodes ≥10 MW7200
Nodes ≥20 MW2104
Available demand capacity (MW)199.17,078.1
Largest node (MW)30.4—
Change in open nodes since June 2026+2-46
Transmission nodes with demand capacity20 of 56290 of 937

What this means for a data center

2 nodes in Palmas, Las publish 20 MW or more of demand capacity, at or above Ampervia’s 20 MW screening threshold for a data center site. Whether a specific request succeeds depends on the operator’s study, the site and the land.

Since March 2026, a Spanish demand access permit is tied to the CNAE activity code declared in the request (RDL 7/2026), so the request has to be filed as a data center from the start.

Method

Source: the CNMC’s national access-capacity service, layers Demanda en Distribución and Demanda en Transporte, publication period August 2026, pulled by Ampervia on 2026-10-12. Comparison period: June 2026.

  • Distribution: each node’s published available capacity (CAP_DISPONIBLE, MW) for new demand, summed and counted by province.
  • Transmission: a Red Eléctrica node is counted as showing demand capacity if any of its published demand categories is above zero.
  • Province names are as published by the CNMC. Ampervia does not publish node or municipality detail.
  • Published capacity is indicative and changes as permits are granted, lapse or are surrendered. Only the network operator can confirm capacity for a specific request.