FLAP-D grid connection thresholds for data centers

In Europe’s core markets, rationing starts at small sizes: 3.5 MW in Frankfurt (above 1 MW in local bottlenecks), 3.5 MVA in Berlin, 5 MVA with a 2,000 m² floor cap in Amsterdam, about 40 MW before a Paris-area project moves from Enedis to RTE, 1 MVA in Dublin, and multi-year waits above 1 MVA in West London.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

In Europe’s core markets, rationing starts at small sizes: 3.5 MW in Frankfurt (above 1 MW in local bottlenecks), 3.5 MVA in Berlin, 5 MVA with a 2,000 m² floor cap in Amsterdam, about 40 MW before a Paris-area project moves from Enedis to RTE, 1 MVA in Dublin, and multi-year waits above 1 MVA in West London.

Key facts

  • Ireland: data centres at or above 1 MVA must show a credible plan to meet at least 80% of annual demand from new Irish renewable generation, within a six-year glide path (Mason Hayes & Curran).
  • Berlin’s first allocation: about 2,300 MVA requested against 365 MVA available (ingenieur.de).
Where connection rules change, by city
CityThresholdWhat happens above itSource
Frankfurt3.5 MW (1 MW in bottlenecks)Pro-rata allocation of new requests by NRMingenieur.de
Berlin3.5 MVAAnnual allocation; 37 of 70 requests got capacity in the first roundingenieur.de, Raue
Amsterdam5 MVA and 2,000 m²Zoning restricts new or expanded data centersGemeenteblad 2026-433374
Paris region≈40 MWConnection moves from Enedis distribution to RTE transmissionGrid Readiness
Dublin1 MVACRU rules: 1–10 MVA needs an autoproducer covering 100% of MICMason Hayes & Curran
West London1 MVAMulti-year waits, some connection dates toward 2035Data Centre Axis

Sources

ingenieur.deRaueGemeenteblad 2026-433374Grid ReadinessMason Hayes & CurranData Centre Axis

Terms on this page: FLAP-D · MVA · MIC · Pro-rata allocation · Autoproducer unit