Home / Rules / Italy DL 21/2026

Italy DL 21/2026: the single authorisation for data centers

Article 8 of Italy’s Decree-Law 21/2026 (converted by Law 49/2026) puts a data center and its grid connection into a single authorisation procedure, and allows a temporary medium-voltage connection in the project documentation, with a definitive solution added later.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

Article 8 of Italy’s Decree-Law 21/2026 (converted by Law 49/2026) puts a data center and its grid connection into a single authorisation procedure, and allows a temporary medium-voltage connection in the project documentation, with a definitive solution added later. It speeds up permitting; it does not create grid capacity.

Key facts

  • Legal basis: DL 21/2026, art. 8, converted by L. 49/2026.
  • A temporary medium-voltage connection solution is accepted, with an obligation to integrate the definitive solution (art. 8, para. 1-bis).
  • Lombardy acts as competent authority in the single procedure for projects in the region (LR 11/2026).

What it means for a site

Permitting and connection run in one track, which shortens time to ready-to-build. Capacity still has to be secured from Terna or the distributor, and Lombardy alone has 44.96 GW of data center requests queued.

Sources

Portale NormativoBibLus (ACCA)

Terms on this page: Single authorisation (Italy) · TSO

Related

All rules →

Looking for powered land in Europe?

Start with the Ampervia Powered-Land Map: candidate sites across six European countries, checked against public records, at zone level, free to explore.