Ireland’s data centre grid connection rules

Ireland’s energy regulator (CRU) decided in December 2025 to tier data centre connections by maximum import capacity.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

Ireland’s energy regulator (CRU) decided in December 2025 to tier data centre connections by maximum import capacity. Below 1 MVA a site is exempt; from 1 to 10 MVA it must provide an autoproducer unit covering 100% of its MIC; and sites at or above 1 MVA must show a credible plan to meet at least 80% of annual demand from new Irish renewable generation within six years.

Key facts

  • Decision published 12 December 2025; initial proposals due 31 March 2026 (Transatlantic Law).
  • De minimis: 1 MVA. Tier 2: 1–10 MVA.
  • 1–10 MVA: autoproducer unit able to meet 100% of MIC (Mason Hayes & Curran).
  • ≥1 MVA: a credible plan to meet at least 80% of annual demand through new Irish renewable generation, within a six-year glide path (Mason Hayes & Curran).

Sources

Terms on this page: MIC · MVA · Autoproducer unit · Behind-the-meter power