Montereau, Paris region: a closed coal plant offered with a fast-track grid connection

Brownfield redevelopment, then build and operate.

By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below

Quick answer

EDF closed its Montereau coal plant in 2004. In 2025 it offered the site to data center developers with a fast-track grid connection, and in November 2025 entered exclusive negotiations with OpCore (iliad and InfraVia) for a data center campus of several hundred MW, an investment of about €4 billion, with first commissioning targeted for 2027.

Timeline

WhenWhat happened
2004Coal-fired plant shut down.
Mar 2025EDF launches calls for expressions of interest for data centers on its former plant sites.
17 Nov 2025Exclusive negotiations with OpCore; ~€4bn, several hundred MW.
2027First commissioning targeted.

What changed between entry and exit

  • The landowner prepared the site and the grid route itself, then ran a competitive process.
  • The developer brings capital and operations.

Capital and counterparties

EDF provides land and grid preparation (typically via construction lease); OpCore (iliad and InfraVia funds) invests about €4bn.

Economics: confirmed and not disclosed

ItemFigureNote
Land termsNot disclosedEDF offers land under construction leases
Developer investment≈€4 billionBuild cost, not land value

Risks and limitations

  • Negotiations, not a completed deal.
  • Scale is far above club-sized projects.

Relevance to Ampervia

Power-plant sites are the grid-rich end of the brownfield market. The playbook (prepare power, then auction to developers) is the same at any size.

Sources

Last checked 2026-10-13. Third-party precedent, not an Ampervia project.