By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-13 · Sources linked below

Quick answer

After the Iberboard paper mill in Alcover entered insolvency in 2024, its majority shareholder, Scranton Enterprises, launched Iberdata: phase 1 secures more than 20 MW so the project qualifies as strategic in Catalonia, phase 2 brings in a partner to design, build and operate the data center, with construction expected to take 2–3 years after the partner signs.

Timeline

WhenWhat happened
Aug 2023Layoffs announced at the mill. Tarragona Digital
Jul 2024Insolvency declared by the Tarragona commercial court. Tarragona Digital
Feb 2026Scranton announces Iberdata: secure >20 MW first, then find an industrial partner.
NextPartner search; 2–3 years of construction after signing. El Nacional

What changed between entry and exit

  • Kept the land while other mill assets are sold.
  • Targeted the 20 MW threshold that unlocks Catalonia’s strategic-project fast track.
  • Plans to bring in an operator partner rather than build alone.

Capital and counterparties

Scranton funds phase 1 (power); a partner is sought to fund and operate the build.

Economics: confirmed and not disclosed

ItemFigureNote
Entry / book valueNot disclosed
Target capacity>20 MW (phase 1)Strategic-project threshold elEconomista
Exit or partner termsNot yet agreed

Risks and limitations

  • Power is not yet confirmed; under RDL 7/2026 the request must be for a data center.
  • No partner signed; timetable depends on it.

Relevance to Ampervia

The same two phases as Ampervia’s model: secure power on a brownfield site, then bring in the capital and operator for the build.

Sources

elEconomistaEl NacionalTarragona Digital

Last checked 2026-10-13. Third-party precedent, not an Ampervia project.