By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below
Spain combines cheaper land and large granted grid access with real bottlenecks where demand concentrates. About 12 GW of access has been granted to data centers against a 2030 forecast of 3.5–4 GW, yet in August 2026 only 9 of Madrid’s 587 distribution nodes offered 20 MW or more. Completed deals near Madrid have priced powered land at about €440,000 per grid MW. Sources (4)YeandelYeandel — Spain granted twelve, planned four↗
CNMCCNMC — access capacity map↗
ActivumSGActivumSG — €11m powered land sale to Pure DC↗
El DebateEl Debate — Radiografía del suelo industrial en Madrid↗
Key facts
- Granted access to data centers: about 12 GW vs 2030 demand of 3.5–4 GW (Yeandel).
- Madrid: 95 of 587 distribution nodes publish demand capacity; 9 offer ≥20 MW; no Red Eléctrica transmission node shows demand capacity (CNMC, August 2026; Ampervia aggregation).
- Meco, Madrid: €11m for 17,650 m² with a 25 MW power agreement (ActivumSG).
- Industrial land along the A-2: about €500/m² in Coslada to €225–250/m² in Alcalá de Henares (El Debate).
- Since March 2026 every demand permit carries a CNAE code and a capacity-reservation charge (BOE, RDL 7/2026).
Where the opportunity is
Outside the most contested Madrid nodes, published capacity is far larger: see the province table. The trade-off is distance from the main interconnection hubs and from the tenants that want Madrid.
What to watch
- Permits granted but never built returning to the grid under RDL 7/2026.
- Land prices rising with logistics and data center demand.
- Whether buyers keep paying per RTB MW, as recent Spanish offers do.
Questions
Can foreign investors buy land in Spain?
Sources
- Yeandel — Spain granted twelve, planned four
- CNMC — access capacity map
- ActivumSG — €11m powered land sale to Pure DC
- El Debate — Radiografía del suelo industrial en Madrid
- BOE — Real Decreto-ley 7/2026
Terms on this page: Access capacity · CNAE lock · Powered land