By Razvan Toma · Founder & CEO, Ampervia · Last checked 2026-10-12 · Sources linked below

Quick answer

It depends on the country. In Spain, no longer by default: since RDL 7/2026 a demand permit is tied to the activity code it was granted for, and changing activity counts as a new installation. The land is still useful, but the data center needs its own request. Elsewhere, reuse is decided case by case with the operator.

Key facts

  • Spain, RDL 7/2026: demand permits must state a CNAE activity code; the connected site must keep that activity for three years or the permit lapses automatically (BOE).
  • Holders of existing permits had six months from the decree’s entry into force to update them, or the permits lapse (BOE).
  • Italy, DL 21/2026: a single procedure covers a data center and its grid connection, and a temporary medium-voltage connection is accepted in the project documentation (art. 8).
  • Lombardy, LR 11/2026: lower construction charges for data centers on brownfield land, higher ones on agricultural land.
Reusing an industrial grid connection, by country (as of October 2026)
CountryCan the plant’s connection carry a data center?Basis
SpainNot automatically: new activity = new installation; file a data center requestRDL 7/2026
ItalyNot settled in law; brownfield is favoured, connection via the single procedureDL 21/2026, LR 11/2026 (Lombardy)
Germany, Netherlands, Ireland, UKCase by case with the operator; large new loads face allocation rulesSee FLAP-D thresholds

What still makes old industrial sites valuable

  • Industrial zoning and existing access.
  • Proximity to substations and high-voltage lines.
  • Brownfield incentives in some regions.
  • A fallback value as industrial land if a data center permit fails.

Questions

Does the three-year rule apply to every request in Spain?
The decree carves out requests tied to urban plans and industrial estates where the infrastructure is ceded to the grid operator. Check the specific case with counsel.
What happened to permits granted before March 2026?
Their holders had six months to declare the activity code; permits not updated lapse automatically.

Sources

Terms on this page: CNAE lock · Access and connection permit · Brownfield site · Single authorisation (Italy)

Related

All answers →

Looking for powered land in Europe?

Start with the Ampervia Powered-Land Map: verified powered-land sites across seven European countries, redacted to zone level, free to explore.